Jeremy Osborne

Home/Mechanical/Industrial experience at Transpave

Industrial experience at Transpave

Industrial placement · Transpave, Minto NSW · Nov 2025 – Feb 2026

The completed spray patcher truck side-on in the workshop at pre-delivery
Testing the completed truck at pre-delivery.

I found this placement myself: I went through the industrial areas near home, applied to the engineering shops there, and Transpave interviewed me and took me on. They design and build bitumen tack coaters and other road maintenance trucks for contractors and councils. It was 60 working days, full-time and unpaid, in a small crew of a welder, a machine operator, the head engineer and me, and I worked on six truck bodies in that time.

Building a truck

Each truck starts as a bare Isuzu cab-chassis. The head engineer designs the body in CAD, parts come back from the laser cutter, and the crew bends, welds and fits them onto a subframe that bolts to the chassis. I came in knowing almost none of it, so for the first weeks I was a sponge: in early every day, never saying no, and taking whatever job was going, mostly alongside the machine operator on the press brake, band saw, mag drill and riveter. On the press brake and the laser cutter I loaded and unloaded the sheet and checked the bend angles, everything short of running the control panel or changing the tooling.

A bare Isuzu cab-chassis outside the workshop
A few weeks in: the bare chassis outside, stripped of what wasn't needed, with the rest repositioned before it went inside.
A steel subassembly modelled in CAD on a workshop monitor
The head engineer's CAD model of a subassembly. Parts go from here to the laser cutter.
The CNC press brake with its control terminal
The CNC press brake and its control terminal.
Steel plates on the bed of a CNC press brake
CNC press brake in operation, bending steel sheet components.
Box section being cut on the band saw
Band saw, cutting box section for the subframe.
Magnetic drill press set up on a C-beam section on the workshop floor
Magnetic drill press, drilling C-beam sections.
The unpainted blue subframe with subassemblies dry fitted on top
The unpainted subframe with the subassemblies dry fitted on top.
Subassemblies strapped up in the paint booth
The paint booth. Smaller subassemblies come off the truck after dry fitting and go in for paint.
The welded spray bar frame subassembly on the workshop floor
The spray bar frame, with a channel at the bottom for the sliding bar.
A forklift carrying the painted lower spray bar
The forklift carrying the painted lower spray bar.

Then came the fit-out: tanks, pumps, hydraulic gear and lighting installed on the body, then final assembly and fault finding before each truck went out. A fit-out job for me was measuring and marking out, drilling the body, then mounting the part and fitting it out. I worked from templates, copied finished parts or photos of them, and mirrored the marks across for the other side. The material ran from 2 mm aluminium up to 20 mm mild steel, with stainless as well.

A pump bolted to a blue chassis rail with tools beside it
A pump mounted on the frame beside the tank, before plumbing.
Hydraulic fluid being pumped into the hydraulic pump reservoir
Pumping hydraulic fluid into the pump reservoir.
Hydraulic hose and fittings from the hose reel on unpainted checker plate during a test fit, an impact driver beside it
Test fitting the hose reel on the unpainted checker plate: position it, mark the holes, drill, then mount it.
The original rear lighting harness and bumper, removed from the base chassis and laid out on the workshop floor
The original rear harness and bumper, off the base chassis. The truck gets custom ones, but the original was kept intact so its wiring could be copied.
Colour-coded crimp connectors joining the wired controller to the hydraulic pump wiring on the truck frame
The wired controller for the hydraulic pumps: tipper up and down, tailgate open and close.
The rear underside of the truck before the tipper and hydraulics
Rear of the truck before the tipper and hydraulics were mounted.
Finished rear with tail lights and do-not-overtake signage
The same end after the LED installation.
Orange aluminium stair assembly mounted on the side of a completed truck
Aluminium stair assembly mounted on the completed truck.
A white pressurised bitumen emulsion tank with a caution sticker and a hose reel
The bitumen emulsion tank and hose reel on a finished unit.
The side of a white truck body with water containers, brackets and a locker fitted
Containers, brackets and a locker fitted to the body.
A black tank and red pump on a steel frame, a finished subassembly
Shipping off a completed bitumen spray and tank subassembly.

The heater controller

One truck was due out that day and the heater on its tank never came on in testing. The temperature controller was set to hold the tank between about 25 and 40 °C, and the shed was already around 30 °C, so it had no reason to switch the heater on. I set a temporary band of 60 to 62 °C so it would cycle quickly, which proved the control logic worked, then put the real range back and explained my reasoning to the head engineer. It was done by 5:15 pm and the truck went out on time.

Side jobs

Between trucks the shop took on other work, from small laser-cut parts to cutting universal beams to length for a Western Harbour Tunnel subcontract.

Cut beams being loaded onto pallets
Loading the cut beams onto pallets after the band saw.
Palletised beams ready for delivery
Palletised and ready to go.
A large aluminium roof panel mid-assembly with tools resting on it
Riveting aluminium sheet assemblies with C-channel reinforcement.
A finished Transpave truck back in the workshop for repairs
A finished truck back in for adjustments.

What I took from it

The biggest thing was seeing how much of the engineering happens at assembly. You build to a drawing, it doesn't go together, and you work out with the crew whether it's the drawing, the part or the order of operations. I already knew what springback was, but this was the first time I saw how much it matters. A part bent a few degrees out gets hammered or cut into place at assembly, while a properly bent one makes the welder's job quicker and easier. I learned to dry fit before committing to anything, and that the paint finish is the first thing a customer judges a truck by.

Somewhere in the last 20 working days it clicked, and I went from soaking it all up to just doing the job. I'd head up to the office for the day's work, or I'd already been told the afternoon before, and get on with it like anyone else on the floor, and the smaller fit-out jobs I was left to do on my own, start to finish. The design and the machine controls stayed with the people trained for them; I was everyone's helper, taking the simpler jobs off their hands so they could get through theirs. At the end they offered me a full-time paid position doing the same work, which I turned down. The learning had levelled off, and it made clear what I want next: a role where the engineering is the job.